  1. The SDLC and its phases
  2. Delivery models: waterfall, V-model, agile, hybrid
  3. SAP Activate
  4. Greenfield, brownfield, bluefield
  5. Documents and deliverables a developer meets
  6. The people in an SAP project
  7. Interview questions

Every SAP project, big or small, follows a software development life cycle (SDLC): someone describes a need, someone designs a solution, developers build it, testers prove it, and the result goes live and is supported. What changes from project to project is the delivery model – one long sequence (waterfall), short repeated cycles (agile), or a mix. SAP's own method for S/4HANA projects, SAP Activate, is such a mix. This page explains the models, the Activate phases, the documents you will receive and write, and the people you will work with. Scrum itself is on page 02.

Part 1 – The SDLC and its phases

The SDLC is the sequence of activities that turns a business need into running, supported software. The names differ between companies, but the six phases are always there:

Phase

Question it answers

Typical output

Developer's part

1 Requirements

What does the business need?

Requirement list, process list, user stories

Ask questions, flag what standard SAP already does

2 Design

How will we solve it?

Functional specification, technical specification, architecture

Write the technical specification, estimate

3 Build

Make it

Code, configuration, transports

Develop, unit test, code review, ATC

4 Test

Does it work, end to end?

Test results, defects, sign-off

Fix defects, support SIT and UAT

5 Deploy

Put it into production

Cutover plan, transports imported, go-live

Release transports, run cutover steps, watch the first runs

6 Maintain

Keep it running and improve it

Incidents, change requests, enhancements

Production support, bug fixes, small changes

  • Requirements → design is where most expensive mistakes start: a misunderstood requirement found in UAT costs far more than a question asked in the design workshop.
  • The phases do not disappear in agile – they are just done in small slices, again and again, inside each sprint.

Part 2 – Delivery models: waterfall, V-model, agile, hybrid

Waterfall: requirements, design, build, test, deploy in one sequence; V-model: each design level on the left mirrored by a test level on the right; agile: repeated sprints that each plan, build, test and review a small increment; hybrid: phased frame with sprints inside

2.1 Waterfall

Each phase is finished and signed off before the next starts: all requirements first, then the complete design, then all development, then all testing, then go-live. Classic SAP projects used ASAP (Accelerated SAP: project preparation, business blueprint, realization, final preparation, go-live and support) – legacy, replaced by SAP Activate.

  • Strengths: clear scope, fixed budget and dates, full documentation, easy to govern and audit.
  • Weaknesses: the business sees working software only at the end; late changes are expensive; risks surface late (in testing).

2.2 V-model

A waterfall variant that pairs every design level with the test level that proves it. The left arm goes down from requirements to code, the right arm goes up through the tests. Test cases are written while the matching design is written, not after the build.

Design level (left)

Proved by (right)

Who tests

Business requirements

User acceptance testing (UAT)

Key users / business

Functional specification / solution design

System integration testing (SIT) – end-to-end processes across modules and interfaces

Functional consultants, testers

Technical design / architecture

Integration testing – objects work together

Developers, testers

Detailed technical specification

Unit testing – one object in isolation

Developer

Code (the bottom of the V)

–

–

2.3 Iterative and agile

Work is split into short, fixed cycles (iterations, in Scrum called sprints, usually 2–4 weeks). Each cycle delivers a small working piece that the business can see and comment on, and the plan is adjusted after every cycle. Requirements live in an ordered backlog instead of a frozen document. The Agile Manifesto (2001) values individuals and interactions, working software, customer collaboration and responding to change – over processes and tools, comprehensive documentation, contract negotiation and following a plan.

  • Strengths: early feedback, priorities can change, risk found early, business stays involved.
  • Weaknesses: needs an available, decisive business; harder to fix scope and price up front; documentation can be neglected.

2.4 Hybrid – what most SAP projects do

SAP programmes have hard dependencies (data migration, cutover weekends, interfaces to many systems, audits), so the overall frame stays phased with formal sign-offs, while design and build run in agile sprints. That is exactly the SAP Activate model: phases and quality gates outside, fit-to-standard backlog in Explore, sprints in Realize.

Aspect

Waterfall

Agile

Hybrid (SAP Activate)

Requirements

Fixed up front in a blueprint

Evolving backlog

Fit-to-standard, then a prioritised backlog of gaps

Delivery

One big go-live

Increment every sprint

Sprints build; one or few go-lives

Change

Formal change request

Re-order the backlog

Backlog in sprints, change request for scope

Testing

Phase after build

Inside every sprint

Unit tests in sprints, then SIT and UAT

Governance

Phase sign-off

Sprint Review

Sprint Reviews plus quality gates

Part 3 – SAP Activate

SAP Activate is SAP's implementation framework for S/4HANA and its other cloud products. It combines SAP Best Practices (ready-made, documented business processes called scope items), the methodology (phases, workstreams, deliverables, quality gates) and tools for guided configuration and project management – today mainly SAP Cloud ALM, where the roadmap tasks, processes, requirements, user stories and tests are tracked. The roadmaps are also published in the SAP Activate Roadmap Viewer.

SAP Activate phases Discover, Prepare, Explore, Realize, Deploy, Run with their main activities, quality gates between phases, fit-to-standard creating the backlog in Explore and sprints in Realize

3.1 The six phases

Phase

What happens

Main results

Discover

Before the project: understand the solution's value, try a trial system, build the business case and the transformation strategy.

Strategy, roadmap, decision to start

Prepare

Project start: plan, team, governance, kick-off, onboarding; system access (in the public cloud the first systems are provisioned).

Project plan, team set up, standards agreed

Explore

Fit-to-standard workshops: consultants show the SAP standard process in a sandbox or starter system, key users confirm the fit or name gaps. Gaps become delta requirements, estimated and prioritised.

Confirmed scope, backlog of delta requirements, design documents

Realize

Build in sprints: configuration, developments (RICEFW, extensions), integration, data migration loads; then integration testing and UAT.

Configured and tested system, migration rehearsed

Deploy

Final preparation: end-user training, cutover (transports, data migration, go/no-go), go-live, then hypercare support.

Productive system, hand-over to support

Run

Operate and improve: support, monitoring, new releases (in the cloud: regular upgrades), continuous improvement.

Stable operations, improvement backlog

  • Quality gates (Q-gates): formal checkpoints at the end of the phases. The deliverables of the phase are reviewed and signed off before the project moves on – the waterfall-style governance that frames the agile work.
  • Workstreams run across the phases, e.g. project management, application design and configuration, extensibility, integration, data management, testing, technical architecture and organisational change management. ABAP developers mostly sit in extensibility and integration.

3.2 From fit-to-standard to sprints

  • Fit-to-standard starts from SAP's standard process, not from the old system: "show us why the standard does not work" instead of "rebuild what we had". This keeps the core clean (see Clean Core › 01 Clean Core).
  • Each gap is written down as a delta requirement (often as a user story), estimated and ordered. Together they form the backlog that feeds Realize.
  • In Realize the team takes backlog items into sprints (typically 2 weeks), builds and unit tests them, and shows them to the key users in a sprint review. Explore builds the backlog; the sprints run in Realize.
  • A gap does not automatically mean code: the options are a different standard process, configuration, key-user extensibility, developer extensibility, or a side-by-side app on SAP BTP.

3.3 Public cloud vs private cloud / on-premise

Topic

S/4HANA Cloud Public Edition

Private Edition / on-premise

Roadmap

Activate roadmap for the public cloud

Activate roadmap for private cloud / on-premise (also covers system conversion)

Fit-to-standard

Mandatory scope items, workshops on SAP-provided systems

More extensive; scope items optional; the team works with the IMG (SPRO)

Configuration

Central Business Configuration (no SPRO)

SPRO / IMG

Development

Only released APIs and ABAP Cloud (key-user and developer extensibility, BTP)

ABAP Cloud recommended; classic ABAP still possible (clean core rules apply)

Upgrades

SAP upgrades on a fixed schedule

Customer plans upgrades

Part 4 – Greenfield, brownfield, bluefield

Approach

Meaning

Typical reason

Greenfield (new implementation)

Build a new S/4HANA system from scratch with SAP Best Practices; migrate master data and open items only.

Re-design processes, leave old custom code behind

Brownfield (system conversion)

Convert the existing ECC system to S/4HANA in place, keeping history, configuration and custom code.

Protect past investment, fastest technical move

Bluefield (selective data transition)

A mix: a new or shell system that takes over selected configuration, data and code from the old one.

Keep some history, re-design some areas, merge or split systems

For a greenfield project, the developer's work is mostly new objects built the clean core way, plus migration objects. Details: CORE ABAP › 01 SAP & ABAP Basics; ABAP on HANA › 02 Migration to S/4HANA & Performance Tools.

Part 5 – Documents and deliverables a developer meets

Document flow in an SAP project: process list (BPML), functional specification, technical specification, code and unit test document, SIT and UAT test scripts, cutover plan, hypercare, with who writes each

Document

What it contains

Written by

Developer's use

BPML / process list

Business Process Master List: every process and step in scope (in Activate: scope items and solution processes).

Functional leads

Find which process an object belongs to

Functional specification (FS)

The business requirement for one object: purpose, rules, fields, layouts, examples, test scenarios.

Functional consultant

Your input – read it, clarify gaps before you build

Technical specification (TS)

How it is built: objects, tables, CDS views, classes, BAdIs, APIs, error handling, performance, authorisations.

Developer

Your design; reviewed by the technical lead

Unit test document (UTD)

Test cases you ran on your object with data and results (screenshots), ABAP Unit results.

Developer

Proof the object works before handover

SIT / UAT test scripts

End-to-end scenarios across objects and modules; UAT = business confirms it is fit for use.

Testers, functional consultants, key users

Fix defects raised against your objects

Cutover plan

Minute-by-minute steps for go-live: transports, data loads, jobs, checks, go/no-go points, rollback.

Cutover manager with all teams

Execute and verify your steps

Hypercare

Period of intensified support right after go-live (often several weeks), then hand-over to support (AMS).

Whole project team

Fix production issues fast

  • Other names you will hear: RICEFW list (all custom objects with their IDs – see CORE ABAP › 01 SAP & ABAP Basics, Part 5), estimation sheet, design / delta design document, code review checklist, transport list, run book.
  • In agile projects, the FS is often lighter: a user story with acceptance criteria plus a short design note. Tickets, transports and change requests: page 03.

Part 6 – The people in an SAP project

People in an SAP project around the ABAP developer: steering committee and project manager, solution architect, functional consultants, BASIS, security, testers, business process owners and key users, change management

Role

Responsible for

You work with them when

Steering committee / sponsor

Budget, scope decisions, go/no-go

Rarely directly

Project manager / delivery lead

Plan, budget, risks, status, resources

Reporting status, estimates, escalating blockers

Solution architect

Overall design across modules, integration and extensibility; clean core decisions

Choosing the extension approach for a gap

Functional consultant (SD, MM, FI …)

Configures the module, runs workshops, writes the FS

Every day: clarifying requirements, testing together

Technical / ABAP consultant

TS, development, unit tests, technical fixes; the technical lead reviews code and sets standards

You are this role

BASIS

Systems, clients, transports, performance, connections (RFC, certificates)

Transport issues, system access, RFC destinations

Security

Roles and authorisations (PFCG), user access

Authorisation objects for your app, missing roles

Integration consultant

Middleware (SAP Integration Suite / CPI, PI/PO), interfaces

Building interfaces end to end

Testers / test manager

Test plan, scripts, defect management

Fixing defects in SIT

Business process owner / key users

Own the business process, approve design, test in UAT, train end users

Demos, UAT, clarifying business rules

Change management / training

Communication, training, adoption by end users

Providing input for training material

In Scrum terms (page 02), the business process owner often acts as Product Owner, and the functional and technical consultants together are the Developers of one Scrum Team.

Part 7 – Interview questions

Q1. What is the SDLC and what are its phases?

The software development life cycle: the activities that turn a need into running software – requirements, design, build, test, deploy and maintain. Waterfall runs them once in sequence; agile runs small slices of them in every sprint.

Q2. Waterfall vs agile – when would you choose which?

Waterfall suits stable, well-known requirements with fixed scope and strong audit needs. Agile suits changing or unclear requirements where early feedback matters. SAP projects usually combine them: phases and quality gates outside, sprints inside.

Q3. What is the V-model?

A waterfall variant where each design level has a matching test level: requirements ↔ UAT, functional design ↔ SIT, technical design ↔ integration test, detailed design ↔ unit test. Test cases are prepared together with the design.

Q4. Name the phases of SAP Activate.

Discover, Prepare, Explore, Realize, Deploy, Run. Quality gates close the phases; fit-to-standard happens in Explore, sprints in Realize, cutover, go-live and hypercare in Deploy.

Q5. What is a fit-to-standard workshop?

An Explore-phase workshop where consultants demonstrate the SAP standard process (Best Practices scope items) and key users confirm it fits or name the gaps. The gaps become delta requirements in the backlog for Realize.

Q6. What is the difference between fit-to-standard and the old blueprint approach?

The ASAP business blueprint documented the customer's processes first and then designed SAP to match, often leading to heavy customising and custom code. Fit-to-standard starts from SAP's standard and only accepts justified gaps – which supports a clean core.

Q7. Greenfield, brownfield, bluefield?

Greenfield: new implementation from scratch. Brownfield: system conversion of the existing ECC system. Bluefield: selective data transition – a mix of new design and selected data and settings from the old system.

Q8. What is the difference between a functional and a technical specification?

The FS describes what the business needs (rules, fields, layouts, scenarios) and is written by the functional consultant. The TS describes how the developer builds it (objects, logic, tables, APIs, error handling) and is written by the developer.

Q9. What are SIT and UAT?

System integration testing checks end-to-end processes across modules and interfaces, run by the project testers. User acceptance testing is the business confirming the solution is fit for use before go-live.

Q10. What is cutover and what is hypercare?

Cutover is the planned sequence of steps that moves the solution into production: transports, data migration, jobs, checks and go/no-go decisions. Hypercare is the period of intensified support right after go-live before hand-over to normal support.

Q11. Who do you work with most as an ABAP developer?

The functional consultant (requirements, FS, testing), the technical lead (design and code review), BASIS (transports, systems), security (authorisations), testers (defects) and, in demos and UAT, the key users.

Q12. How does SAP Activate differ for the public cloud?

The public cloud roadmap uses mandatory scope items, Central Business Configuration instead of SPRO, only released APIs and ABAP Cloud for extensions, and SAP-scheduled upgrades. Private cloud and on-premise allow SPRO and classic ABAP, with clean core recommended.

🏠 Start Here · 02 · Scrum Framework ▶ · Sections: CORE ABAP | OOPS ABAP | ABAP on HANA | Clean Core | RAP | ABAP Points | SAP Fiori | SAPUI5 | Mobile Development (MDK) | BTP Foundations | BTP Development | CAP | SAP Build | ABAP on BTP | Integration Suite | SAP Business AI | SAP BASIS | Security | SAP SDLC