Business Processes & Configuration

PS ABAP · Logistics ·

Open the interactive lesson →
  1. The project lifecycle at a glance
  2. Structuring and scheduling
  3. Cost and revenue planning
  4. Budgeting
  5. Availability control
  6. Release and execution
  7. Progress analysis, POC and earned value
  8. Billing customer projects
  9. Results analysis and revenue recognition
  10. Settlement
  11. Closing: TECO and CLSD
  12. Investment programs (IM) in brief
  13. Key customizing and Fiori apps
  14. Interview questions

This page follows a project through its life: build the structure, plan costs and revenues, approve and release a budget, control it with availability control, execute (purchasing, materials, confirmations, cost postings), measure progress, bill the customer, recognise revenue, settle and close. For each step you get the business purpose, the t-codes and Fiori apps, and the customizing behind it. Objects and tables: page 02; postings to FI / CO / SD / MM in detail: page 04.

Part 1 – The project lifecycle at a glance

Every project, simple or complex, passes the same phases. The system status moves with it (CRTD → REL → TECO → CLSD, page 02 Part 7) and decides which transactions are allowed in each phase.

Project lifecycle: structure (CJ20N) → cost and revenue planning (CJ40, CKCM) → budget (CJ30, CJ32) with availability control → release (REL) → execution (purchasing, reservations, confirmations CN25 / CATS, cost postings) → progress analysis (CNE1) → billing (milestone, DP91) → results analysis (KKA2) → settlement (CJ88) → TECO and CLSD

Phase

Status

Main t-codes (GUI)

Result

1 Structure

CRTD

CJ20N, CJ91 / CN01 templates

Project definition, WBS, networks, milestones

2 Plan

CRTD

CJ40, CJR2, CKCM, CJ42; network costing

Plan costs and revenues

3 Budget

CRTD / BUDG

CJ30, CJ32, CJ37, CJ38, CJ34

Approved and released budget, availability control active

4 Release

REL

CJ20N (Edit → Status → Release)

Postings and procurement allowed

5 Execute

REL

ME21N, MIGO, CN25 / CN27, CAT2 + CAT5, FB50 / KB21N

Commitments, actual costs, confirmations

6 Progress

REL

CNE1 / CNE2, CNE5

POC, earned value

7 Bill

REL

VA01 + billing plan, DP91, VF01 / VF04

Invoices, revenue

8 Revenue recognition

REL / TECO

KKA2 / KKAJ or event-based revenue recognition

WIP, POC revenue, reserves

9 Settle

REL / TECO

CJB1 / CJB2 (rules), CJ88 / CJ8G

Costs moved to AuC, asset, cost center, CO-PA

10 Close

TECO → CLSD

CJ20N, CNMASSSTATUS

No more postings; archiving later

Part 2 – Structuring and scheduling

Part 3 – Cost and revenue planning

Planning gives the expected cost and revenue of the project. PS offers several methods with increasing detail; the planning profile (OPSB) defines which are allowed, the planning horizon and the costing variant.

Method

T-code

Level of detail

When to use

Structure (hierarchical) planning

CJ40 change, CJ41 display

One amount per WBS element and year, no cost elements

Early phase, rough estimates

Detailed planning by cost element / activity type

CJR2 (and planning layouts)

Cost element and activity input per WBS and period

Precise plans, activity-based planning

Unit costing

From CJ40

Quantity × price lines (materials, activities, variable items)

Bottom-up estimates per WBS

Easy Cost Planning

CKCM; execution services

Model-based costing with characteristics (costing model)

Quick, repeatable estimates; writes ACDOCP as of S/4HANA 2022

Network costing

Automatic in CJ20N / CN22

Activities: work × activity price, external price, general costs, components

Projects with networks – plan comes from logistics

Revenue planning

CJ42 (structure), sales order / billing plan

Revenue per billing element

Customer projects

  • Plan values are versions of CO (version 0 = plan / actual version). Several plan versions allow best case / worst case comparisons.
  • S/4HANA: classic PS planning still works on-premise; the strategic direction is planning into ACDOCP (Fiori planning apps, SAP Analytics Cloud integration).

Part 4 – Budgeting

The budget is the approved cost frame. It is usually entered top-down on the upper WBS levels and distributed downwards; availability control checks against it. The budget profile (OPS9) defines time frame, overall vs annual values, currency and availability control activation.

Transaction

Purpose

Effect

CJ30 / CJ31

Original budget change / display

Budget per WBS element (overall and per year)

CJ32 / CJ33

Release budget change / display

Only the released part can be used when availability control is set to 'released'

CJ37

Budget supplement

Adds budget (top-down or to a WBS element)

CJ38

Budget return

Gives unused budget back to the superior WBS element

CJ34

Budget transfer

Moves budget between WBS elements, also between projects

IM52

Budget distribution from an investment program

Program position → investment WBS (Part 12)

  • Budget values are stored in BPGE (overall) and BPJA (annual) with budget documents (BPBK, BPEG / BPEJ); every budget change is a document.
  • Budgeting sets status BUDG; the budget can be locked by a user status so that only supplements / returns change it.

Part 5 – Availability control

Availability control (AVC) checks every cost-relevant posting – purchase requisition, purchase order, goods issue, invoice, journal entry, confirmation – against the budget. It compares the assigned value (commitments + actual costs) with the budget and reacts when a tolerance limit is reached.

Plan, original budget, released budget; assigned value = commitments (COOI) plus actual costs (ACDOCA); tolerance limits per activity group with actions warning, warning with mail, error; CJBV activate, CJEN reconstruct

Setting

Where

What it does

Activation type

Budget profile (OPS9)

0 = cannot be activated, 1 = activated automatically when budget is allocated, 2 = activated in the background when the usage reaches a set percentage

Usage basis

Budget profile

Check overall budget or annual budget; against total or released budget

Tolerance limits

IMG: Project System → Costs → Budget → Define Tolerance Limits

Per budget profile, activity group (all transactions or groups such as purchase requisitions, purchase orders, actual postings) and usage %: action 1 warning, 2 warning with mail to the person responsible, 3 error (posting blocked)

Exempt cost elements

IMG (budget)

Cost elements that are never checked, e.g. internal settlement

  • CJBV activates AVC for projects that were budgeted before activation; CJBN reconstructs the AVC values (after customizing changes or data corrections).
  • Typical setup: 90 % warning, 100 % warning with mail, 105 % error. AVC runs on the level where the budget is; lower WBS elements without their own budget are checked against their superior.
  • Developer note: an AVC error is a normal error message of the posting transaction (e.g. the PO cannot be saved). Interfaces that create POs or journal entries with WBS account assignment must expect it in the BAPI return table and route it to the person responsible, not retry blindly.

Part 6 – Release and execution

Release (status REL in CJ20N, partial release possible) allows actual postings and procurement. From then on, costs reach the project from many sources:

Source

How

Posting / document

External activities / services

Network activity PS02 / PS05 creates a purchase requisition; purchasing creates the PO

EBAN → EKPO with account assignment N (network) or P (WBS); commitment in COOI; GR and invoice post actuals

Stock materials

Components with item category L create reservations; goods issue to the network or WBS

RESB; movement type 281 (GI for network) or 221 (GI for project); project stock Q for engineer-to-order

Non-stock materials

Item category N → purchase requisition for direct procurement

EBAN, PO, GR posts the cost directly

Internal work

Confirmation of hours on network activities

CN25 individual, CN27 collective confirmation; AFRU; activity allocation to the WBS / network

Time sheets

Employees record hours in CATS (CAT2 / Fiori My Timesheet) on activities or WBS elements

CAT5 transfers to PS (confirmations), CO activity allocation for WBS

Direct postings

Journal entries, travel, invoices with WBS account assignment

FB50, MIRO, FB60 with WBS; ACDOCA-PS_PSP_PNR

Internal allocations

Activity allocation, overhead surcharges, assessments

KB21N, costing sheet at period end

  • Every requisition and PO is checked by availability control at commitment time, not only at invoice time – that is why budget overruns are stopped early.
  • Project stock (valuated or non-valuated) keeps materials reserved for one WBS element; MRP plans it separately (special stock Q, table MSPR – MM ABAP › 03).

Part 7 – Progress analysis, POC and earned value

Progress analysis measures how far the project really is, independent of the costs spent. It calculates the percentage of completion (POC) per WBS element or activity and the earned value.

Term

Meaning

Formula / source

BCWS (planned value)

Budgeted cost of work scheduled – what should be done by today

Plan cost × planned POC

BCWP (earned value)

Budgeted cost of work performed – value of what is really done

Plan (or budget) cost × actual POC

ACWP (actual cost)

Actual cost of work performed

Actual costs on the object

Cost variance

Over / under cost

BCWP − ACWP

Schedule variance

Ahead of / behind schedule

BCWP − BCWS

  • Measuring methods (per object and value category): start-finish rules (0-100, 20-80, 50-50), milestone technique, estimation, time-proportional, degree of processing, quantity-proportional, secondary proportionality, cost-proportional.
  • T-codes: CNE1 individual, CNE2 collective progress analysis; CNE5 progress analysis report (on-premise and private cloud; not delivered in the public edition, which uses Fiori alternatives).
  • Progress (POC) is a controlling figure; recognising revenue from it is a separate step (Part 9).

Part 8 – Billing customer projects

A customer project links a sales order (or contract) item to the billing element WBS (VBAP-PS_PSP_PNR). Revenues post to that WBS element. Two billing methods dominate:

Method

How it works

Key objects

Milestone billing

The sales order item has a billing plan with dates and percentages linked to project milestones. When the milestone's actual date is entered in PS, the billing block of that date is removed and the date is billed in VF01 / VF04.

Billing plan FPLA / FPLT, MLST with billing flag, billing documents VBRK / VBRP

Resource-related billing (RRB)

DP91 reads the actual costs (hours, materials, expenses) of the WBS / network, groups them into dynamic items according to the DIP profile (ODP1) and creates a debit memo request; it is billed into an invoice.

DIP profile, debit memo request, billing document

Periodic billing / down payments

Fixed amounts per period, or down payment requests in the billing plan

Billing plan, down payment clearing

  • The full order-to-cash view of service contracts with WBS elements and DP91 is in SD ABAP › 02 Part 7; postings and account determination on page 04.

Part 9 – Results analysis and revenue recognition

Costs and revenues of a long project rarely match period by period. Revenue recognition makes the profit appear in the right periods and values the work in process.

Approach

How

Availability

Results analysis (RA)

Period-end run KKA2 (individual) / KKAJ (collective) per WBS with a results analysis key and version: calculates WIP, reserves, POC revenue or cost of sales; settlement then posts the result to FI and CO-PA

On-premise / private cloud (classic)

Event-based revenue recognition (EBRR)

Revenue recognition postings are made with each event (cost posting, billing) in real time in ACDOCA; period-end only for adjustments

S/4HANA – the strategic method; the only one in the public edition

  • RA methods: revenue-based, cost-based POC, completed contract, quantity-based. The result is visible in the WBS element's line items and in margin analysis after settlement.
  • Architect point: EBRR removes the period-end RA run and gives real-time margins, but it changes the posting logic – decide it during the design, together with the ledger and CO-PA set-up (page 06).

Part 10 – Settlement

Settlement moves the costs (and revenues) collected on WBS elements and networks to their final receivers. It is defined by a settlement rule per object (COBRA / COBRB) and controlled by the settlement profile (OKO7).

Costs on WBS elements and network activities settled periodically: investment WBS to asset under construction then final assets; customer project to profitability segment; overhead project to cost center or G/L; networks to their WBS element; CJB1 / CJB2 rule generation, CJ88 / CJ8G run

Receiver

Category

Typical project

Asset under construction / fixed asset

FXA (the AuC is an asset)

Investment project

Profitability segment

PSG

Customer project (results from RA / EBRR)

Cost center

CTR

Overhead, internal, R&D project

G/L account

G/L

Overhead project, special cases

WBS element

WBS

Network activities to their WBS; sub-projects to a main WBS

Sales order item / order

SDI / ORD

Special cases

  • Settlement rules: entered manually in CJ20N or generated by CJB1 / CJB2 with a strategy (e.g. WBS to its responsible cost center, activities to their WBS).
  • Run: CJ88 individual, CJ8G collective settlement, period by period after all other period-end steps (overhead, RA). Settlement type PER periodic, FUL full settlement.
  • Investment projects: the investment profile in the project profile creates an AuC when the WBS element is released; periodic settlement capitalises costs on the AuC; at completion a line-item settlement distributes the AuC to the final fixed assets (FI-AA, FICO ABAP › 03).

Part 11 – Closing: TECO and CLSD

Part 12 – Investment programs (IM) in brief

Investment Management (IM) sits above projects for capital spending. An investment program is a hierarchy of program positions (e.g. per division and plant) that holds the capital budget for a fiscal year. Investment measures – WBS elements or internal orders – are assigned to program positions; budget is distributed to them (IM52) and cannot exceed the program budget.

  • Appropriation requests capture investment ideas with variants and approvals before a project exists; approved requests become investment measures.
  • The investment profile on the WBS adds the capital-spending logic: AuC, depreciation simulation, settlement to assets.

Part 13 – Key customizing and Fiori apps

Key customizing (SPRO → Project System)

Setting

T-code / IMG

Controls

Project profile

OPSA

Defaults and all other profiles of a project (page 02 Part 6)

Network type / network profile

OPSC / OPUU

Order type, number range, costing variants / user defaults, control keys

Coding mask

OPSJ

Edit mask of project and WBS keys

Planning profile

OPSB

Cost planning methods, horizon, costing variant

Budget profile

OPS9

Budget time frame, AVC activation

Tolerance limits

IMG Costs → Budget

AVC warning / error thresholds per activity group

Settlement profile

OKO7

Receivers, settlement obligation, allocation structure

Status profile

OK02

User statuses and allowed business transactions

DIP profile

ODP1

Resource-related billing: sources, characteristics, material determination

Results analysis key / version

IMG Revenues and Earnings

RA method, valuation, posting rules

Version / simulation profile

OPTS / OPS4

Project versions and simulation

Fiori apps (examples)

App

Use

Since / note

Project Cost Overview, Project Cost Line Items

Plan / actual costs of project, WBS, networks and assigned orders

S/4HANA 2022 FPS1 (on-premise / private cloud)

Project Schedule

Gantt chart scheduling – successor of the project planning board

S/4HANA 2021

Project Claim Overview

Claim management (issues and claims with costs)

S/4HANA 2022

Event-Based Revenue Recognition – Projects

Monitor and adjust real-time revenue recognition

S/4HANA

My Timesheet (and Manage Timesheet)

Time recording on WBS elements and activities

CATS-based

Enterprise project apps

Create and control projects in the public edition

Public cloud

  • The GUI transactions CJ20N, CJ40, CJ30, CJ88 remain the daily tools on-premise; Fiori covers reporting and new functions first.

Part 14 – Interview questions

Q1. Walk me through the lifecycle of an investment project in PS.

Create the project with an investment profile (CJ20N), plan costs (CJ40), get budget from the investment program (IM52) or enter it (CJ30), release it so an AuC is created, procure and post costs under availability control, settle periodically to the AuC (CJ88), set TECO, settle the AuC to final assets and close the project.

Q2. Plan vs budget vs released budget?

Plan is the cost estimate (CJ40, CJR2, network costing). Budget is the approved limit (CJ30). Released budget (CJ32) is the part that may be used now; availability control can check against it instead of the total budget.

Q3. How does availability control work?

When active (budget profile, CJBV), every commitment and actual posting is compared with the budget. Tolerance limits per activity group trigger a warning, a warning with mail or an error at a usage percentage. CJBN reconstructs the values.

Q4. Which transactions are used for budget changes?

CJ30 original budget, CJ32 release, CJ37 supplement, CJ38 return, CJ34 transfer; IM52 for distribution from an investment program. Each change creates a budget document.

Q5. How do costs get onto a network activity?

Internal activities through confirmations (CN25, CATS + CAT5); external activities and non-stock components through purchase requisitions, POs, goods receipts and invoices; stock components through goods issue 281; plus overhead and allocations at period end.

Q6. Explain earned value.

Progress analysis (CNE1 / CNE2) calculates the POC. Earned value BCWP = plan cost × actual POC, compared with planned value BCWS and actual cost ACWP: BCWP − ACWP is the cost variance, BCWP − BCWS the schedule variance.

Q7. Milestone billing vs resource-related billing?

Milestone billing bills fixed amounts from the sales order billing plan when project milestones are reached. Resource-related billing (DP91, DIP profile) bills the actual costs of the project through a debit memo request.

Q8. Results analysis vs event-based revenue recognition?

RA (KKA2 / KKAJ) is a period-end run that calculates WIP, reserves and POC revenue and posts them via settlement. EBRR (S/4HANA) posts revenue recognition with each cost or billing event in real time and is the only option in the public edition.

Q9. What is a settlement rule and how is it created?

The receivers and percentages for settling a WBS element or network (COBRA / COBRB), within the limits of the settlement profile (OKO7). Created manually in CJ20N or generated by CJB1 / CJB2 with a strategy; executed with CJ88 / CJ8G.

Q10. What happens at TECO and at CLSD?

TECO blocks new planning and requisitions but allows follow-up costs from open commitments; open reservations are no longer relevant for MRP. CLSD is set after the final settlement and blocks actual postings to the WBS element and hierarchy changes.

Q11. Which customizing objects would you check first if a project behaves unexpectedly?

The project profile (OPSA) and the profiles it points to – planning (OPSB), budget (OPS9) with tolerance limits, settlement (OKO7), status profiles (OK02) – plus network type and profile (OPSC / OPUU) for networks.

Q12. As an architect, how would you design revenue recognition for customer projects in S/4HANA?

Prefer event-based revenue recognition for real-time margins and fewer period-end steps, use milestone or resource-related billing as the business requires, and align the WBS billing elements, profit centers and margin analysis characteristics early – RA only when a classic method is legally needed on-premise.

🏠 Start Here · ◀ 02 · Structures & Data · 04 · Integration & Reporting ▶ · Sections: CORE ABAP | OOPS ABAP | ABAP on HANA | Clean Core | RAP | ABAP Points | SAP Fiori | SAPUI5 | Mobile Development (MDK) | BTP Foundations | BTP Development | CAP | SAP Build | ABAP on BTP | Integration Suite | SAP Business AI | SAP BASIS | Security | SAP SDLC